Strengthen Lampung Province’s Electricity, Rekadaya Elektrika Builds 150 kV Substation Teluk Ratai and Pagelaran

In this edition we will discuss the Progress of the 150 kV Teluk Ratai Substation Development Project located in Pesawaran city and Ext 2 LB 150 kV Pagelaran Substation (GI) located in Pringsewu city, Bandar Lampung Province.

The project entrusted by PT PLN (Persero) Southern Sumatra Development Unit (UIP SBS) to PT Rekadaya Elektrika (RE) includes Procurement, Mechanical Electrical Installation and Civil Works. Until the first quarter of 2023, the overall work progress for the construction of GI Teluk Ratai and GI Pagelaran has reached 83.74%.

The work that is being completed by the team in the field for GI Teluk Ratai is in the form of switchyard fence work, drainage and control basin work, construction of control buildings and substation area complex road work.

As for GI Pagelaran itself, construction work has been completed 98.5% and is completing electromechanical work, which is carried out in parallel with the preparation of individual tests towards commissioning. Furthermore, waiting for the readiness of the Gedong Tataan Transmission and GI (not carried out by RE), then the plan is to conduct an individual test and be ready to be energized in June.

Read More
DCIM100MEDIADJI_0020.JPG

REKADAYA ELEKTRIKA COMPLETED LINE BYPASS MODIFICATION OF FEED WATER PIPE AND STEAM DRAIN HPH OF PLTU TANJUNG AWAR-AWAR

This time, REINISTE will raise a story about one of the Availability Improvement Program (AIP) jobs that is currently almost completed by the Rekadaya Elektrika (RE) project team, namely the Procurement Work of the Feed Water Pipe Bypass Line Modification and Steam Drain High Preassure Heater (HPH) owned by PT PLN Nusantara Power Tanjung Awar-awar Generating Unit located in Tuban, East Java.

It is said to be almost complete, because currently the progress of work which includes mechanical, instrument and electrical work which is the responsibility of RE has reached 100%. And currently leaving the commissioning work, namely RR or Reability Run for 2×24 hours at maximum load to ensure the feasibility of operation of the HPH Feed Water and Steam Drain pipe installations and the implementation of operational training.

Read More
DCIM100MEDIADJI_0003.JPG

Rekadaya Elektrika Efforts Complete Unit GT 6 PLTG Pesanggaran 2×100 MW

Good news has come again from the PT Rekadaya Elektrika (RE) project team on the Island of the Gods, namely the Pesanggaran 2×100 MW Gas Power Plant (PLTG), which is a relocation project from Grati. After last November 1 2022, one of the Pesanggaran 2×100 MW (GT 5) PLTG units has officially operated and became one of the suppliers of electricity supply at the G20 Summit event.

Thanks to the well-established collaboration between team members in the field and the Indonesia Power and
Cogindo teams, several milestone stages for the GT 6 PLTG Pesanggaran unit have been successfully implemented according to the target, as follows:

  • First Firing (06 March 2023)

  • First Synchro (07 March 2023)

  • Performance Test (11 March 2023)

  • Reliability Run (12 March 2023)

The purpose of carrying out the Performance Test (PT) and Reliability Run (RR) is to determine the reliability of the GT 6 unit and as part of the stages required for the issuance of an Operational Worthy Certificate (SLO) from Pursetif PT PLN (Persero). The contribution made by RE so that the implementation of the Performance Test and Reliability Run was carried out successfully, including ensuring that the common system, grounding system, fire fighting system and cooling system can operate properly.

As of the 3rd week of March, the progress of work in the field which is RE’s responsibility has reached 93%. The scope of work that remains is the completion/finishing of common facility areas such as permanent road access, drainage, security post and trench cover.

Through the enthusiasm of the project team to make a real contribution in strengthening the reliability of electricity supply in the Bali Region and its surroundings, it is hoped that the 2×100 MW Pesanggaran PLTG will be fully completed in mid-2023 according to the set targets.

Read More

Rekadaya Elektrika Ready to Contribute to the Construction of the 150kV High Voltage Cable Line (SKTT) Project – Tambak Lorok III

Monday, 06 March 2023 the signing of the contract agreement took place between PT PLN (Persero) and PT Multi Kencana Niagatama (MKN) – PT Rekadaya Elektrika (RE) for the 150 kV High Voltage Cable Line Project (SKTT) – Lorok Pond III. The contract signing took place at Lt. 9 Main Building of PT PLN (Persero) on Jl. Trunojoyo blok M-1 No. 135, South Jakarta. Signed directly by the Director of Project Management and Renewable Energy of PT PLN (Persero) Mr. Wiluyo Kusdwiharto and the Main Director of PT MKN Mr. Dicky Susanto as the chairman of the KSO.

Also attending the signing procession as RE representatives were Mr. Jonner MP Pardosi as the Main Director and Mr. Vernon S. As well as the entire Executive Vice President (EVP) of PT PLN (Persero Tampubolon as the Director of Marketing & Business Development.) including EVP of Procurement Planning Mr. Anang Yahmadi, EVP of T&D Procurement Executive Ms. Julita Indah, EVP Construction for Java Bali Nusra Maluku Papua Ms. Ratnasari Sjamsuddin and General Manager of PT PLN UIP JBT Mr. Djarot Hutabri . This project is an accelerated project where KSO RE and MKN are committed to completing the High Voltage Cable Channel Project (SKTT) III – Tambak Lorok in 5 months of work and a maintenance period of 12 (twelve) months from the date of the Minutes of Handover of Work (BASTP) .

Read More

Progress Pembangunan PLTS PT Pertamina Power Indonesia

Since the execution of the contract signing (work order-WO) on 04 October 2022, currently the progress of PT Pertamina Power Indonesia’s internal PLTS development work for clusters 3, 4 and 5 is almost complete. The progress of work in the field for the two clusters has reached 95% and is ready to operate.

As of March 3 2023, the three clusters that are being worked on by PT Rekadaya Elektrika are:

Cluster 3  :

  • PGN-Ketapang office building, West Jakarta with a total capacity of 36,000 Wp;

  • Pertamina Central Hospital located in South Jakarta with a capacity of 120,000 Wp

  • Pelita Air Service Pondok Cabe, South Tangerang (2 location points) with a total capacity of 100,000 Wp

Cluster 4 :

  • Pertamina Trans Kontinental – Kabil in Batam City, Riau Archipelago with a total capacity of 12,000 Wp

Cluster 5 :

  • Pertamina Geothermal Energy – Lahendong in Tomohon, North Sulawesi with a total capacity of 20+20 kWp.

Rekadaya Elektrika through the project team in the field continues to contribute to developing renewable energy through the construction of new renewable energy-based power plants.

 

Read More

ENERGIZED TL 275 KV PAYAKUMBUH – GARUDA SAKTI LINE #2

Another joyful moment was delivered by colleagues from the 275 kV Payakumbuh – Garuda Sakti Transmission line project team. This is because on February 14, 2023 it has succeeded in energizing line 2, which is a ground steel wire (GSW), whereas previously, on January 31, 2023, it had succeeded in energizing line 1, which is an optical ground wire (OPGW).

The success of applying voltage to the two 275 kV Payakumbuh – Garuda Sakti TL line circuits located in Kapalo Koto Village, Payakumbuh District, is expected to immediately support system reliability and optimize the 275 kV Payakumbuh – Perawang SUTET Transmission which spans 2 provinces, namely West Sumatra (Payakumbuh ) and Riau Province (Perawang) and is the backbone of the Sumatra transmission line.

Our appreciation goes to the project team in the field led by Charles GP Siburian as the Project Manager (PM). Hopefully this spirit of success will spread to other projects.

Read More

Energized GI 150 kV Kuala Pembuang

At the beginning of February 2023, very proud news came again from the RE project team, the 150 kilo Volt (kV) substation (GI) project, a cross-Kalimantan development. The RE project team immediately energized the 150 KV Kuala Pemburan 2 Line Bay 1 Trafo Bay substation project located in Pematang Panjang Village, Seruyan Hilir Timur District, Seruyan Regency, Central Kalimantan.

Not spared from several technical and non-technical obstacles, the RE project team continues to make progress in contributing to the strengthening of electric power, especially in Kuala Pemburan and in general for Seruyan District.

Read More

Project Trasmission Line 70 kV GI Namrole-Namlea

Still around Eastern Indonesia, this time we will visit South Buru Island-Maluku, the location of one of the transmission line projects being worked on by PT Rekadaya Elektrika (RE). The 70 kV Namrole – Namlea Transmission Line project will connect two substations (GI), namely Namrole GI and Namlea GI, which cross 7 villages with a total distance of 90.3 kilometers.

Entering the end of January, the overall progress of the work has reached 84.12% (leading from the target of 80.77%). Currently, the total land that has been acquired has reached 93.16%, with a total of 216 foundations that have been completed, of the target of 234 tower foundations (92.31%). (72.65%).

The Namrole-Namlea 70 kV TL Project is also not free from a number of technical and non-technical challenges. One of the obstacles faced was the rocky location of the land, which made it difficult for the field team to work. However, the team in the field has exerted maximum effort, including using jack hammers and heavy equipment (excavators) to level the roads and the foundation construction sites.

The RE project team continues to make progress in the construction of this transmission line, so that it can immediately meet the electricity needs of the people on South Buru Island, Maluku.

Read More

Contribution of PT Rekadaya Elektrika in the Development of the Bali LNG Terminal Project

Tuesday, January 17, 2023 at PT Titis Sampurna’s Head Office in the Sovereign Building, South Jakarta, the signing of the Cooperation Contract Agreement between PT Rekadaya Elektrika (RE) and PT Dewata Clean Energy took place for the Liquefied Natural Gas (LNG) Terminal Development Project located in Bali.

The LNG Terminal Infrastructure Development is a supporting facility project that functions to provide primary energy needs for PT Indonesia Power’s Gas Power Plant (PLTG) located in Pesanggaran, Bali.

PT DEB is a joint venture between Perusda Bali and PT Titis Sampurna. The signing procession was attended by Mr. Jonner MP Pardosi as the Main Director of RE and witnessed by Mr. Vernon S Tampubolon as the Director of Marketing and Business Development and other RE Directors. Meanwhile, from PT DEB, Mr. Cokorda Alit Indrawardana as the Main Director attended, and also accompanied Mr. Ananta as the Director of Business Development at Perusda Bali, as well as the Board of Directors of PT Titis Sampurna namely Mr. Thomas Aquino as Managing Director and Mr. Ferry Fahiza as Finance & Corporate Director.

Read More

Trasmission Line 150 kV Piru – Kairatu

This time PT Rekadaya Elektrika (RE) will review the progress of the work of one of the transmission projects located in Central Maluku and Seram districts, namely the Piru-Kairatu 150 kV Transmission Line.

The electricity infrastructure project owned by PLN UPP Maluku which is entrusted to Rekadaya Elektrika, will later combine 2 (two) Piru Substations (GI) and Kairatu GI, with a total of 123 towers.

As of the 2nd week of January, work progress had reached 45.487% (leading) where land clearing and foundation construction work had progressed significantly.
The total installed foundations are currently 72 foundations (of the target of 123 foundations), with a transmission line of 91 kms. TL 150 kV Piru – Kairatu is planned to be energized at the end of 2023.

Like the projects that Rekadaya Elektrika has worked on, the Piru-Kairatu TL project also faced several technical problems in the field during the construction process. Such as access to material alerts which is difficult because of the hilly terrain and high rainfall in the last few months.

However, the RE Project Team continues to strive and provide the best results to achieve progress in the construction of this transmission line, so that it can immediately meet the electricity needs on Seram Island, Maluku. Electrical Rekadaya will always play an active role and make a real contribution in building and increasing the reliability of the electricity system throughout Indonesia.