In this edition, REINSITE will highlight the progress of 2 works being completed by PT Rekadaya Elektrika (RE), located in the Cirata area, Purwakarta – West Java. These are the 150 kV Transmission Line (TL) project and the 150 kV Substation (GI) built to support the operation of the Cirata 145 MV Floating Solar Power Plant.
· Cirata 150 kV Transmission Line Project
Rekadaya Elektrika was trusted to work on 9 towers (T.01 -T.09) with a total length of 3.11 KMR.
Scope of work: civil work (foundation services), electrical and mechanical work (erection services, stringing and commissioning services).
Progress as of Week 2 April 2023: civil works in the form of foundation construction for 8 points and erection and stringing works for 9 towers have reached 100%.
Target energized: May 2023
· Cirata 150 kV Substation Project
Scope of work: civil work in the form of MTU foundation construction services, electrical & mechanical work in the form of MTU erection services and test & commissioning (RLB).
Progress as of Week 2 April 2023: some civil works such as construction of Gantry foundation, High Voltage (HV) equipment foundation, cable trench, and Gantry erection have been completed with a progress of 49.16%. While some of the electrical and mechanical works that have been completed include Grounding Grid, Busbar Conductor, installation of insulators and installation of HV Apparatus.
Target energized: June 2023