Our Contacts

Building 18 Office Park Lt. 18
Jl. T.B. Simatupang No.18, Pasar Minggu,
South Jakarta - 12520
Indonesia

info@plnnpc.com

+62 (021) 2787 1818
+62 (021) 2770 8558

Category: RE INSITE

Read More

REKADAYA ELEKTRIKA REVITALIZES MAIN STRUCTURE CONVEYOR PLTU TANJUNG JATI

In order to support electricity in Central Java Province, PT Rekadaya Elektrika (RE) is working on the Revitalization Steel Structure Conveyor project on the Jetty at PLTU Tanjung Jati. As the main contractor of the project is PT Komipo Pembangkitan Jawa Bali (KPJB) Tanjung Jati.

The scope of work that is the responsibility of Rekadaya Elektrika is preparatory work, procurement of steel structure (conveyor) materials and repair / revitalization of steel structure. Until mid-2023, the progress of the revitalization work of the main structure of the conveyor PLTU Tanjung Jati B, overall progress has reached 8,770%.

Obstacles from the technical and non-technical side (nature) are of course often experienced by the project team in the field, however the project team remains enthusiastic to play an active role in making a real contribution to providing light and increasing the reliability of the Central Java province’s electricity system through the Tanjung Jati PLTU.

Read More

Boiler Retubing Work Unit 3 of PLTU Indramayu

Rekadaya Elektrika (RE) successfully completed the Unit 3 Boiler Retubing Procurement Project owned by PT PJB UBJOM PLTU Indramayu which has been functioning and operating properly.

The Boiler Retubing Procurement Project is led directly by Mr. Mach Novviali as Project Manager. The project consists of 2 stages of work, namely:

  • ·       Boiler tube fabrication stage which was completed on March 21, 2022.
  • ·       Installation stage of the boiler tube which was completed on February 09, 2023.

The Rekadaya Elektrika project team successfully completed the installation work within 3 months, and currently the unit 3 boiler retubing project is entering a 24-month maintenance period.

Read More

REKADAYA ELEKTRIKA SUCCEEDS CARRY OUT BACKFEEDING SOFIFI PLTU 2X3 MW

RE-Insite again delivered encouraging news regarding the progress of the construction of one of the Steam Power Plant (PLTU) projects undertaken by PT Rekadaya Elektrika (RE) which is located in the Maluku islands, precisely in the North Halmahera region.

As of the 4th week of July 2023, work in the field has reached a progress of 35.305%.  Currently the project team in the field is working to complete the installation of pipes and power cables, as well as the testing & commissioning stages of Low Voltage (LV) & Medium Voltage (MV) Switchgear and testing & commissioning for transformers. And on Saturday July 8, 2023, the RE project team has successfully carried out backfeeding.

What is backfeeding? Backfeeding is a stage of the power plant development process that utilizes a temporary connection of electrical energy from PLN’s 20 kV system, which is used for testing the readiness of equipment in the generating system.

PT PLN (Persero) UIP Maluku Papua as the owner also expressed appreciation and gratitude for the hard work given by the RE project team for successfully carrying out one of the milestones, namely Backfeeding in accordance with the initial target. While advising that the RE project team remains focused on completing the next stage of work.

By upholding the value of Amanah, RE is committed to completing the construction process of the Sofifi 2×3 MW PLTU project to bring light across the country.

Read More

Progress Project of Transmission Line 70 kV Substation Namrole – Substation Namlea

This time we visit one of the transmission line project locations that is being worked on by PT Rekadaya Elektrika (RE). It is the 70 kV Namrole – Namlea Transmission Line project which will connect two substations (GIs) namely Namrole GI and Namlea GI, which crosses 7 villages with a total distance of 90.3 kilometers.

In the middle of 2023, the overall work progress has reached 89.54%. Currently the total land that has been acquired has reached 93.16%, with a total of 229 foundations that have been completed from the target of 235 tower foundations (94.01%). While the total towers that have been successfully established are 222 towers from the target of 235 towers (76.35%).

Rekadaya Elektrika continues to strive to achieve progress in the construction of this transmission line, so that it can immediately meet the electricity needs of the people in Maluku, especially South Buru Island.

Read More

Energized Substation 150 kV PENDO

The PT Rekadaya Elektrika (RE) Project Team again delivered encouraging news while showing an attitude of trust through the implementation of energized one of the substation projects, namely the Construction of Extension 2 Transformer Bay GI 150 kV PENDO on Saturday, May 27, 2023.

The work, which was led by Pongging as Project Manager, successfully carried out the provision of voltage after obtaining a Letter of Recommendation on May 26, 2023. Representing the Project team, he expressed his gratitude for all the support provided by the head office management team so that the 150kV PENDO GI project could be energized.

PT PLN (Persero) UIP JBB as the owner also expressed his appreciation and gratitude to RE for successfully completing the construction of the 2 transformer bay extension of GI 150 kV Pendo, although it is still not 100% perfect.

Read More
default

WORK PROGRESS RELOCATION PLTG EAST HALMAHERA 111 MW

After at the end of 2022, the PT Rekadaya Elektrika project team successfully completed the construction of 2 units of the East Halmahera Gas Power Plant (PLTG), now 3 other generating units are also being accelerated so that they can operate immediately.

The PLTG owned by PT PLN (Persero), which was relocated from the Sumatra region (Jakabaring and Batanghari), will aim to supply electrical energy for PT Aneka Tambang’s ferronickel smelter activities in East Halmahera. With a total capacity of 111 MW consisting of 5 generating units.

As of the end of April the work progress has reached 89%, with the scope of work currently being completed is civil construction work, electrical work (including installation of Transformers, MV Panels, LV Panels and Batteries) and mechanical work (including Water Treatment Plant, Waste Water Treatment Plant, and Fire Fighting).

Read More

Construction Progress of TL and GI 150 kV Cirata, to Support the Cirata 145 MV Floating Solar Power Plant Project

In this edition, REINSITE will highlight the progress of 2 works being completed by PT Rekadaya Elektrika (RE), located in the Cirata area, Purwakarta – West Java. These are the 150 kV Transmission Line (TL) project and the 150 kV Substation (GI) built to support the operation of the Cirata 145 MV Floating Solar Power Plant.

·        Cirata 150 kV Transmission Line Project

Rekadaya Elektrika was trusted to work on 9 towers (T.01 -T.09) with a total length of 3.11 KMR.

Scope of work: civil work (foundation services), electrical and mechanical work (erection services, stringing and commissioning services).

Progress as of Week 2 April 2023: civil works in the form of foundation construction for 8 points and erection and stringing works for 9 towers have reached 100%.

Target energized: May 2023

·        Cirata 150 kV Substation Project

Scope of work: civil work in the form of MTU foundation construction services, electrical & mechanical work in the form of MTU erection services and test & commissioning (RLB).

Progress as of Week 2 April 2023: some civil works such as construction of Gantry foundation, High Voltage (HV) equipment foundation, cable trench, and Gantry erection have been completed with a progress of 49.16%. While some of the electrical and mechanical works that have been completed include Grounding Grid, Busbar Conductor, installation of insulators and installation of HV Apparatus.

Target energized: June 2023

Read More

ENERGIZED SUTT 150 KV TAMBAK LOROK III

Good news again came from PT Rekadaya Elektrika (RE) project site team colleagues, precisely for the 150 kV Tambak Lorok III High Voltage Cable Line (SKTT) project in the city of Semarang, Central Java. Of the 10 line bays that are the scope of work, the RE site team has successfully energized 1 line bay, namely the Pandean Lamper 1 compartment line bay on Monday, April 17, 2023. What is special is that the RE team managed to energize earlier than the planned schedule.

The withdrawal / installation of the underground cable (UGC), which connects the 150 kV Tambak Lorok III Gas Insulated Substation (GIS) with the existing 150 kV Tambak Lorok GIS aims to evacuate the power generated by the Tambak Lorok 3 PLTGU, so that it is expected to further strengthen the reliability of the electricity system in the Central Java area, especially the city of Semarang and its surroundings.

The scope of work that is the responsibility of RE includes, among others, pulling cables for 10 line bays, installing distributed thermal sensing, engineering work to commissioning to achieve UGC operations. The implementation of this work is projected to be completed in the third quarter of 2023.